← Back to portal
Six Peak Capital · LV Construction · Operations

LV Construction Operations Portal

Project financials, contract backlog, and staffing for the Six Peak Construction LA (LV Construction) GC platform. Use the section tabs or ← → arrows to move through the deck.

Now showingOverview
01 / 09
Financials Jul 2026 · Buyout Jul 2026
01 · Overview · As of July 31, 2026

LV Construction — operations at a glance

A snapshot of the active construction book, contract backlog, and year-to-date financial performance across the Six Peak Construction LA portfolio. Eleven jobs are in the book — five under construction, two that submitted first pay applications in July (Francis and Riverton), two mobilizing, and two pending capitalization (Scott & Klump) — against $131.4M of current contract value and a $93.3M backlog now that the Francis and Riverton contracts are carried in the KPI workbook.

LIVE DATA: Figures on the Overview, Active Projects, Financial Results, and Staffing tabs are sourced from the 07.2026 Consolidated Financials (Job KPI workbook, as of July 31, 2026). The Pipeline tab is live from LV ROM estimates issued in July 2026, and the Project Buyout tab is live from the monthly Buyout Report workbooks in Box. Safety inspection results on Operational Metrics are live from the third-party inspection program.
Portfolio SnapshotContract · backlog · YTD financials
Jobs in the Book
11
5 under construction · 2 on first pay app · 2 mobilizing · 2 pending
Current Contract Value
$131.4M
+$0.41M net change orders · Francis and Riverton now included
Backlog
$93.3M
$38.1M billed to date (29%)
YTD Net Profit (FY26)
$2.20M
7.7% net margin · $28.53M revenue
Performance & PeopleMargin · buyout · headcount
YTD Gross Profit
$4.08M
14.3% gross margin · $0.84M of it is the Francis bond line billed before its August costs
Job-to-Date Net Profit
$2.56M
6.7% net margin · $38.1M JTD revenue
Buyout Savings
$266.7K
Cumulative · detail on Project Buyout tab
Headcount
21
Jan–Jul avg $196K/mo · July $216K · ~$286K/mo projected from Sep · see Staffing
Read of the book: The portfolio carries $131.4M of current contract value across eleven jobs, from Crenshaw in wrap-up (80% complete) to the pending Scott & Klump. The June pack showed $74.2M because Francis and Riverton were carried as “pending buyout”; both are now in the KPI workbook at their contract values ($42.79M and $14.34M) and both submitted their first pay applications in July — mostly bond premiums, mobilization and deposits, not trade work. $38.1M has been billed, leaving a $93.3M backlog. Year-to-date the platform has produced $28.53M of revenue at a 14.3% gross margin and a 7.7% net margin ($2.20M). July alone added $7.03M of revenue and $1.77M of gross profit — but $0.84M of that gross profit is the Francis bond line billed to the owner in the first pay application; the $314K surety premium (invoiced August 4) and the ~$694K due to Krueger under the bonding program both land in August, so most of it is timing, not margin. Crenshaw, Ramsgate, Califa and Whipple remain the profit drivers; Nelrose and the mobilizing jobs are still carrying startup overhead. Beyond the book, LV is pursuing $160.4M of new work across 834 units — see the Pipeline tab, anchored by the Tom Taggart–sourced Beverly bid and six HVN projects.
02 · Pipeline · As of July 2026

New-work pipeline — $160.4M in pursuit

Seven projects totaling 834 units are in active pursuit, all priced with the LV ROM estimator off the committed-bid library. Beverly — a 94-unit market-rate bid sourced by Tom Taggart — anchors the private-side pipeline, and the HVN relationship has produced six projects: four deals holding CTCAC LIHTC awards (tax-credit awards to HVN — LV has issued GC bids, with Dickens, Moorpark and Riverton as the primary targets), plus a 75-unit private deal and a 340-unit estimate.

LIVE DATA: Values are LV ROM hard-cost estimates issued July 2026 (LV ROM Engine v2.1.3, committed-bid library), filed per project in Dropbox under Construction / 02 Projects / Pursuit. ROMs are budget benchmarks, not GMPs or bids.
Pipeline SnapshotROM value · units · sourcing
Pipeline ROM Value
$160.4M
7 projects in active pursuit · vs $74.2M current book
Pipeline Units
834
94 market-rate · 740 affordable
HVN Projects
6
4 LIHTC-awarded (LV targeting 3) · 75u private · 340u est.
Beverly · Tom Taggart
$25.0M
94-unit bid submitted Jul 22 · new client sourced
Beverly — sourced by Tom Taggart: Tom originated and leads the 4623 Beverly Blvd pursuit (developer Josh Tavakoli, The Larchmont at Beverly) — a 94-unit, 102,131 SF, 7-story podium project with market-rate finishes. LV’s ROM was issued July 22 at $25.0M ($245/SF); the owner’s budget is $22–22.5M and a value-engineering pass is underway to close the gap. This is a new third-party client relationship for the platform, sourced and led by Tom.
Pursuit DetailFrom LV ROM estimates · July 2026
ProjectProgramUnitsGSFROM Hard Cost$/SF$/UnitStatus
Beverly 4623 · Tom TaggartMarket-rate (12 ELI) · Tavakoli94102,131$25.03M$245$266KBid Submitted · VE
Dickens (Sherman Oaks)HVN · CTCAC 4% LIHTC7555,518$15.32M$276$204KLIHTC Award · LV Target
Moorpark (Studio City)HVN · CTCAC 4% LIHTC10265,935$18.44M$280$181KLIHTC Award · LV Target
Riverton 5642 (NoHo)HVN · CTCAC 4% LIHTC7536,483$11.32M$310$151KLIHTC Award · LV Target
Federal (West LA)HVN · CTCAC 4% LIHTC7340,454$11.96M$296$164KLIHTC Award · Bid Issued
Troost 5614 (Valley Village)HVN · Non-LIHTC (private)7557,181$15.19M$266$203KROM Issued Jul 30
Farralone (Canoga Park)HVN · 100% affordable340240,050$63.18M$263$186KEstimate Sent Jul 30
Total834597,752$160.44M$268$192K

ROM hard-cost values from LV ROM Engine v2.1.3 client estimates: Beverly issued 7/22/26; HVN Round 2 awarded-4 portfolio re-run 7/12/26 ($57.04M across 325 units, $287/SF avg); Troost and Farralone issued 7/30/26. All figures are rough-order-of-magnitude benchmarks from LV’s committed-bid history — not GMPs or contractual bids. “LIHTC Award” denotes HVN’s CTCAC 4% tax-credit award on the project — not an LV contract award; LV has issued GC bids on all four. LV’s primary targets are Dickens, Moorpark and Riverton, which cluster in the Valley near LV’s active jobs; Federal (West LA) sits outside that cluster and is a lower-priority pursuit. All four are 100% affordable, Type IIIA, non-prevailing-wage basis, bonded.

Why it matters: The pipeline is 2.2x the current $74.2M book. The HVN relationship alone represents $135.4M across 740 units — four deals holding CTCAC LIHTC awards on which LV has issued GC bids (LV’s targeted three, Dickens/Moorpark/Riverton, total $45.1M across 252 units), plus two additional projects HVN sent directly (the 75-unit Troost private deal and the 340-unit Farralone estimate). On the market-rate side, Tom Taggart’s sourcing of Beverly opens a new third-party GC client. Every pursuit was priced with the LV ROM estimator, turning bids around in days off the committed-bid library.
03 · Active Projects & Backlog

The active construction book

Eleven jobs totaling $131.4M of current contract value. Crenshaw is in wrap-up; Ramsgate, Califa, Whipple and Nelrose are mid-build; Francis and Riverton have submitted first pay applications; Lexington and Acama are mobilizing; Scott and Klump are pending capitalization. Percent billed against percent complete — the over/under-billing view the June pack was missing — is now in the table.

JobCurrent ContractBilled to DateBacklog% Billed% CompleteOver / (Under)Job EndStatus
Crenshaw$15.21M$11.88M$3.33M78%80%-1.5 ptsNov 2026Wrap-Up
Ramsgate$25.99M$12.70M$13.29M49%54%-4.7 ptsJul 2027On Schedule
Califa$13.43M$5.46M$7.96M41%40%+0.4 ptsJun 2027On Schedule
Whipple$15.35M$5.07M$10.28M33%32%+1.1 ptsJun 2027On Schedule
Nelrose$4.26M$1.70M$2.57M40%40%+0.3 ptsAug 2027On Schedule
Francis$42.79M$0.85M$41.94M2%0%+1.9 ptsJan 20291st pay app · started Aug 2026
Riverton$14.34M$0.40M$13.94M3%2%+1.0 ptsFeb 20281st pay app · bond, demo, deposits
LexingtonPending buyout—————Mar 2028Pre-construction · Sep 2026 start
AcamaPending buyout—————Apr 2028Pre-construction
ScottPending—————Apr 2028Pending capitalization
KlumpPending—————Apr 2028Pending capitalization
Total$131.37M$38.07M$93.30M29%———

Current Contract = Original Contract + Net Change Orders ($0.41M across the book). Backlog = Current Contract − Billed to Date. Francis and Riverton are now carried at contract value in the KPI workbook (the June pack showed them as pending buyout); Lexington and Acama have not completed buyout; Scott and Klump are pending capitalization and carry mobilization entries only. % Billed is billed-to-date over current contract; % Complete is cost-to-date over current budget; Over / (Under) is the difference in points — positive means billed ahead of cost. Ramsgate is the one to watch at -4.7 points under-billed. Job-end dates are the model completion months; Crenshaw’s KPI record still shows July 2026 and its schedule shows substantial completion December 1.

04 · Financial Results

Job financial results · YTD & job-to-date

Profit and loss by job for fiscal-year-to-date 2026 and over the full life of each project. The book is running a 14% gross margin and a 8% net margin year-to-date, 15% gross / 7% net on a job-to-date basis. Both are flattered by July: Francis booked $932K of revenue against $22K of cost, $839K of it the bond line billed before the surety premium and the Krueger payment were recorded. Excluding Francis, YTD is 12% gross and 6% net.

Year-to-Date (FY2026)Through July 31, 2026
JobRevenueCost of SalesGross ProfitGM%OverheadNet ProfitNM%
Crenshaw$5,715,396$5,061,895$653,50111%$250,944$402,5577%
Ramsgate$10,017,451$8,954,450$1,063,00111%$453,523$609,4786%
Califa$5,161,101$4,567,590$593,51111%$320,042$273,4695%
Whipple$4,735,789$4,168,501$567,28812%$283,236$284,0526%
Nelrose$1,618,097$1,455,434$162,66310%$189,808($27,145)-2%
Francis$932,055$22,289$909,76698%$249,707$660,05971%
Riverton$354,912$219,594$135,31838%$71,753$63,56518%
Lexington$0$50($50)—$34,451($34,501)—
Acama$0$50($50)—$32,153($32,203)—
Scott$0$100($100)—$0($100)—
Klump$0$50($50)—$0($50)—
Total$28,534,801$24,450,003$4,084,79814%$1,885,617$2,199,1818%
Job-to-Date (Life of Project)Cumulative since job start
JobRevenueGross ProfitGM%Net ProfitNM%
Crenshaw$11,921,402$1,361,25211%$616,5565%
Ramsgate$12,874,476$1,604,64612%$783,0536%
Califa$5,465,029$745,14214%$400,9207%
Whipple$4,979,193$698,63614%$391,2208%
Nelrose$1,618,097$162,66310%($97,929)-6%
Francis$932,055$909,71698%$469,80950%
Riverton$354,912$135,31838%$63,56518%
Lexington$0($50)—($34,501)—
Acama$0($50)—($32,203)—
Total$38,145,164$5,617,27315%$2,560,4907%

Source: 07.2026 Consolidated Financials (KPI). Francis and Riverton submitted their first pay applications in July ($932K and $355K of recognized revenue). On Francis $839K of the $852K billed is the bond line, billed at 100%; the $314K CBI premium (invoiced August 4, bond effective August 10) and the $366K cash due to Krueger when the bond line funds both post in August, so most of the job’s $910K gross profit is timing. Riverton’s $400K is bonding ($212K billed against a $104K budget), demolition ($74K, fully costed), the elevator deposit and mobilization. That is why both flip from a loss in June to a profit here; the job-level workbook carries a deferred-revenue adjustment on each job (Francis +$80K, Whipple ($93K), Nelrose ($79K), Riverton ($45K)) that bridges billings-based margin to the recognized figures shown. Lexington and Acama show only mobilization overhead; Scott and Klump have de minimis entries and no job-to-date history yet.

05 · Project Buyout · As of July 2026

Project buyout · cost certainty across the book

How much of each job's budget is locked into executed subcontracts and purchase orders — and how much remains exposed to market pricing. The four reporting jobs are 82% bought out in aggregate, with $12.2M still open to buy, concentrated at Riverton.

LIVE DATA: Sourced from the monthly Buyout Report workbooks maintained per job in Box (Whipple & Califa as of July 2026; Riverton June 2026; Ramsgate April 2026 PM report). Refreshed monthly with the pay-application cycle.
Buyout SnapshotCommitted vs. budget · reporting jobs
Active Book Bought Out
82.4%
$57.0M committed of $69.2M budget · 4 reporting jobs
Remaining to Buy
$12.2M
Open to market pricing · $7.4M at Riverton
Buyout Savings
$266.7K
Cumulative across the book
Pipeline Pre-Buyout
3 jobs
Acama · Lexington · Francis buying before start
Buyout by JobFrom monthly Buyout Reports
JobUnitsBudgetCommittedRemaining to Buy% Bought OutΔ vs Prior MoAs OfStatus
Whipple91$15.35M$14.08M$1.27M91.7%+5.2 ptsJul 2026Nearly Bought
Califa76$13.43M$12.19M$1.23M90.8%+5.6 ptsJul 2026Nearly Bought
Ramsgate116$26.12M$23.85M$2.27M91.3%—Apr 2026Nearly Bought
Riverton80$14.34M$6.92M$7.41M48.3%—Jun 2026Early Buyout
Total363$69.23M$57.04M$12.18M82.4%——

Budget = total job budget per each job's Buyout Report; Committed = executed subcontracts and POs; % Bought Out = Committed ÷ Budget, as reported in each workbook. Whipple and Califa each added ~5 points of buyout during July. Ramsgate and Riverton report in the richer PM-report format (invoiced, cost-to-complete, projected final cost); standardizing all jobs on one template is recommended so this table rolls up mechanically. Crenshaw (wrap-up) and Nelrose are excluded pending current reports.

Read on buyout: Whipple, Califa and Ramsgate have locked more than 90% of their budgets into executed trade contracts — cost risk on those jobs is largely retired. The book's open exposure sits at Riverton ($7.4M remaining to buy at 48.3%), which is early in its buyout cycle. On the pipeline, Acama, Lexington and Francis are already running pre-construction buyout — jobs are entering the book with trades committed before capitalization, de-risking the backlog before ground-break.
06 · Staffing

Staffing & payroll allocation

On booked actuals, staffing averaged ~$196K/month January through July 2026 ($1.37M total; July $216K); the seven-month average smooths biweekly pay-period timing, including May's three-period month. As Francis and Riverton mobilize in August, Lexington in September and Acama in November, the Base Case roster steps up to a projected ~$286K/month across 25 people: payroll grows with the book, not ahead of it. People are shared across jobs, so per-job counts below overlap; unique headcount was last confirmed at 21.

Job / FunctionPeople on JobMonthly Payroll% of Total
Crenshaw5$20,97310%
Ramsgate9$35,23116%
Francis4$24,78811%
Nelrose7$23,07711%
Califa9$30,79614%
Whipple9$30,41114%
Riverton6$26,20412%
Lexington3$6,2823%
Acama3$6,2833%
Business Development1$1,5381%
Estimating1$4,1542%
Internal Management2$4,2312%
Office Management1$1,3461%
Payroll / Paperwork1$5380%
Total—$215,852100%
Unique Headcount
21
Last confirmed allocation · people shared across jobs
Jan–Jul 2026 Average Payroll
$196K
Booked actuals Jan–Jul ($1.37M total) · July $216K
Projected · All Four Jobs Running
~$286K
Base Case roster from Sep 2026 · 25 people · Francis, Lexington, Riverton, Acama
Field vs. G&A Payroll
95% / 5%
$204.0K on jobs · $11.8K G&A functions

Sources: 07.2026 Consolidated Financials (STAFFING) and the Base Case model (Actuals + Personnel, Jul 24 roster). “People on Job” counts everyone who charged time to that job in July; individuals appear on multiple jobs (61 job-assignments across the book), so the column intentionally does not total to unique headcount (21). Average: booked payroll (5000-1000) Jan through Jul was $144.6K / $150.7K / $178.9K / $187.7K / $295.9K / $198.6K / $215.9K, averaging $196.0K/month; the average smooths biweekly pay-period timing (May carried three pay periods). Projection: the Base Case Personnel roster has Francis and Riverton-Denny mobilizing August 2026, Lexington September 2026 (moved from August at the July close) and Acama November 2026 (moved from September on August 23); from September the roster carries 25 people at ~$286K/month on a salary basis ($268K field / $18K corporate; the roster shows 29 lines because Grady LaKamp, Joe LaKamp, Pedro Rosalas and Greg Smith are each split between field and office/G&A allocations), rising to ~$297K and 26 people in December when the Francis APM joins, then settling at ~$276K and 25 people from January 2027 after a planned year-end departure. No headcount reduction occurred at any point.

07 · Operational Metrics

Operational health

Safety, change orders, and revenue pacing across the active portfolio. Every figure on this tab is live — revenue and change-order dollars from the consolidated financials, safety results from the third-party inspection program.

LIVE DATA: Revenue figures are sourced from the 07.2026 Consolidated Financials; safety inspection results are live from the monthly third-party inspection program (Safety Compliance Company), filed per job in Box.
Revenue-to-Date (FY26)
$28.53M
14.3% gross margin
Job-to-Date Revenue
$38.15M
Life-of-project
Net Change Orders (book)
$0.41M
Current contract vs. original
Safety — Unsat. Findings
0
Latest filed: 52 items (Ramsgate, Jun 16) · July reports not yet filed
Safety ProgramThird-party inspections · live

Monthly site safety inspections

Independent inspections by Safety Compliance Company at each active site, monthly since November 2025. The latest inspection (Ramsgate, June 16, 2026) covered 52 items with 39 satisfactory and zero unsatisfactory findings — all employees and subs observed in PPE, no fall hazards present. Reports are filed per job in Box.

Compliance & certifications

  • IIPP and Heat Illness Prevention programs current and on file
  • OSHA 30 certifications held by field supervision (Delgado, Terriquez, Torres)
  • CPR training records current (2024 & 2025 cycles)
Methodology: Revenue and net change-order dollars are sourced from the consolidated financials; safety inspection results are sourced from the third-party inspection reports filed per job in Box.
08 · 7/31/26 Financials · January–July 2026 Actuals

July 31, 2026 financials — LV Construction & Six Peak Capital

Seven months of 2026 actuals (January–July, Yardi close) for both entities, with cash positions at July 31. The GC is profitable and accelerating; Six Peak corporate carries the platform burn that the fee and BD programs are built to cover. Consolidated year-to-date nets to $1.20M on the entity ledgers, of which $1.33M is July alone — a month that carries $0.84M of the Francis bond line billed to the owner before the premium and the Krueger payment were recorded. The full-year Base Case stands at $0.51M because the models still carry July job margin on the billing curve rather than the ledger; see the basis note below.

LIVE DATA: Entity-level actuals from the 07.2026 Base Case model (Actuals tab — monthly Yardi close, Jan–Jul 2026). Cash positions are the July 31 bank balances as loaded in the model on August 28; the forward cash build was restated August 29.
Year-to-Date SnapshotJan–Jul actuals · both entities
LV (GC) Net Income · YTD
$2.05M
On $28.53M revenue · July $1.45M, $0.84M of it the Francis bond premium
Six Peak Net Income · YTD
($0.85M)
July ($118K) · run rate ~($120K)/mo before fee programs
Consolidated NI · YTD
$1.20M
Entity ledgers · models carry ($0.08M) YTD, see basis note
Cash at 7/31
$0.41M
LV $0.28M · SP $0.12M · FY26 proj. ending $1.72M
LV Construction (GC) · Monthly P&LYardi close · Jan–Jul 2026
LineJanFebMarAprMayJunJulYTD Total
Total Revenue$1,453,791$3,022,522$2,672,216$3,692,358$4,416,062$6,252,263$7,025,596$28,534,808
Gross Profit$218,757($51,001)$594,185$447,358$465,537$641,351$1,766,650$4,082,837
GC Overhead($260,602)($260,309)($351,938)($73,432)($437,915)($323,454)($321,512)($2,029,162)
GC Net Income($41,845)($311,309)$242,247$373,927$27,622$317,897$1,445,138$2,053,677

Revenue ramp tracks the book mobilizing: $1.45M in January to $7.03M in July, of which $1.25M is the first Francis and Riverton pay applications in a single month. February's negative gross profit reflects trade-cost timing on early-cycle billing; May net income was compressed by the third biweekly payroll period and a $74K warranty adjustment. April GC overhead ($73K) looks far lower than the other months (roughly $260K to $438K) because of a one-time $251K credit: payroll for self-performed trade work was reclassified out of overhead and into job costs, where it belongs as a cost of the work. Before that credit, April overhead was ~$325K, right in line with March and June; nothing was cut. May carries a smaller $82K credit of the same kind, masked by its third biweekly payroll period. July gross profit of $1.77M is the item to read carefully: $1.15M of it is margin on trade billing (a 18% spread on $6.41M of trade billing against a book that normally runs near zero on trades), driven by the first Francis and Riverton pay applications. $839K of the Francis billing and $212K of Riverton’s is the bond line, recorded as revenue in July; the surety premiums ($314K Francis, $104K Riverton already booked) and the ~$694K due to Krueger under the bonding program post in August, where the models already carry them, so on a matched basis the two bond lines are roughly a wash and about $0.95M of July’s gross profit is timing. The job-level KPI workbook already carries an $80K deferred-revenue adjustment on Francis and ($45K) on Riverton.

Six Peak Capital · Monthly P&LYardi close · Jan–Jul 2026
LineJanFebMarAprMayJunJulYTD Total
Total Revenue$34,115$34,115$34,115$34,115$34,115$333,115$78,115$581,805
Total Expenses($198,828)($192,502)($255,024)($195,905)($250,030)($201,582)($195,563)($1,489,434)
Interest, Tax & Amort (true-up)—————$53,642($935)$52,707
Six Peak Net Income($164,713)($158,387)($220,910)($161,790)($215,915)$185,174($118,383)($854,924)

Recurring SP revenue is fee income (Edgemont management fee, Ramsgate and Crenshaw development fees, ~$34K/month). June includes a $299K non-cash revenue item and a $54K interest/tax/amortization true-up, which turn the month positive; July carries the first $44K of 12th & Fir developer fee. The underlying run rate is roughly ($120K) to ($160K) a month — the burn the Uplifters and BD fee programs are designed to cover. Note the July close removed the Six Peak-to-LV overhead allocation from the projection entirely: it was never booked in either ledger, so these entity figures are the true split.

Basis note: This tab is the entity-level P&L (Yardi close per the Base Case model). The Financial Results tab shows the same book on a job-level basis from the KPI workbook, which allocates overhead by job and excludes entity-level true-ups — its $2.20M YTD GC net profit versus the $2.05M entity figure here is a presentation difference, not a discrepancy. What the models carry for July is different again: the July P&L was loaded on the overhead, fee and Six Peak lines, but the five jobs under construction are still on the July billing curve ($4.38M billed, $4.48M cost) rather than the ledger ($6.41M, $5.26M), so the models show July consolidated net income of $85K against $1.33M on the ledgers and a year-to-date of ($77K) against $1.20M. The models stay on the curve by decision. Most of the $1.24M is a one-month timing gap on the bonding program, not margin: the first Francis and Riverton pay applications billed $1.05M of bond lines in July, and the money that goes out against them — the $314K Francis surety premium (CBI invoice of August 4) and the ~$694K due to Krueger as the Francis bond line funds — posts in August, where the models already carry it. Net of the bond lines, July ran about $0.3M ahead of the curve.
09 · Board Q&A · Appendix · August 2026

Board questions — answered from the current data

This appendix responds to the questions raised ahead of the August board call: what in the HVN relationship is actually signed, funded and on site; cash today and over the next thirteen weeks; budget versus actuals; WIP and retention; the Krueger wage-compliance issue; a tracker for deals where Six Peak holds a stake or promote; and the job-level dashboards, risk register and warranty reporting that the pack does not yet carry.

SOURCES: Cash, 13-week look-forward, budget-vs-actual and retention are pulled directly from the 07.2026 Base Case model as restated August 29 (Model, Budget vs Actual and Retention tabs — actuals through the July Yardi close, cash build re-opened at August 1 on the July 31 bank balances, liquidating distribution removed from the cash build). Job status, buyout and safety figures cross-reference the Active Projects, Project Buyout and Operational Metrics tabs of this deck. The wage-compliance answer summarizes the July 14–17, 2026 correspondence with Justin Krueger and outside counsel.
Q1 · HVN — what is signed, funded and on siteA definitive status ladder

Short answer: five jobs in the book are HVN work already committed to LV — Califa and Whipple building today, and Lexington, Riverton and Acama contracted and awaiting their LIHTC closings. Those three are committed work, not pursuits: the GMPs are set, pre-construction buyout is running, and the only thing between them and ground-break is the tax-credit closing — the developer’s and syndicator’s process, not ours. The six HVN projects on the Pipeline tab are pursuits, not awards: the “LIHTC Award” label there refers to HVN’s CTCAC 4% tax-credit award on the deal, not an LV contract award. The table below is the definitive list the pack was missing — every job in the book against the same five-stage ladder.

JobContract SignedFinancing Closed / FundedOn Site% CompleteBilled to DateStatus
CrenshawYesYesYes80%$11.88MWrap-Up
RamsgateYesYesYes54%$12.70MBuilding
Califa HVNYesYes · bondedYes40%$5.46MBuilding
Whipple HVNYesYes · bondedYes32%$5.07MBuilding
NelroseYesYesYes40%$1.70MBuilding
FrancisYes · $42.79M GMPYes · closed 8/13/26Yes0%$0.85M · 1st pay appBuilding
Lexington HVNYes · $12.99M GMPAwaiting LIHTC closing · Sep 2026 modeled (was Aug)No0%—Pre-Construction
Riverton HVNYes · $14.34M GMPAwaiting LIHTC closing · Aug 2026 modeledNo2%$0.40M · 1st pay appPre-Construction
Acama HVNYes · $21.26M GMPAwaiting LIHTC closing · Nov 2026 modeled (was Sep)No0%—Pre-Construction
KlumpPending capitalizationNo — raising ~$1.5M pref (w/ Scott)No0%—Pending Capital
ScottPending capitalizationNo — raising ~$1.5M pref (w/ Klump)No0%—Pending Capital
On site & funded6 jobs$131.4M current contract value incl. Francis and Riverton——$38.07M billed

Status ladder built from the Active Projects tab and the Base Case model Projects sheet (contract value, start month, bonding). Five jobs in the book are HVN: Califa and Whipple are under construction and bonded through the ICON National / Travelers program; Lexington, Riverton and Acama are committed to LV and waiting on LIHTC closings — $48.6M of contracted GMP that converts to billing as those closings occur. The six HVN projects on the Pipeline tab (Dickens, Moorpark, Riverton 5642, Federal, Troost, Farralone — $135.4M of ROM value across 740 units) carry no signed LV contract and no LV award; four of them hold CTCAC 4% LIHTC awards granted to HVN as developer, against which LV has issued GC bids. This column will be carried forward on every pack so the signed / funded / on-site distinction is explicit rather than inferred.

Q1a · Contingencies on the near-term GC startsBeyond Francis · what gates each start
StartModeled StartGating ContingencyVisibility We HaveRating
FrancisAug 2026Resolved. Closed August 13, 2026; construction started in August. First pay application submitted in July ($852K, of which $839K is the bond line; bond effective August 10).Closing tracked directly with the lender and syndicator; carry cost of ~$25K/month is booked and visible monthly. Each month of slip = ($163K) FY26 NI and ($155K) FY26 cash.Green
Riverton HVNAug 2026LIHTC closing, plus the largest open cost exposure in the book — 48.3% bought out with $7.41M still to buy.Monthly Buyout Report in the richer PM format (invoiced, cost-to-complete, projected final cost). Buyout is the item to watch, not the close.Red
Lexington HVNSep 2026LIHTC closing. Committed to LV; pre-construction buyout is running ahead of ground-break.Pre-con buyout log; GMP trued to $12.99M this cycle. No adverse signals as of the June close.Amber
Acama HVNNov 2026LIHTC closing plus bonding — Acama sits in the Tier 2 bonding band (3.25% rate vs 0.72–0.74% on the Tier 1 jobs), so bond cost is a live GMP input.Pre-con buyout running; bonding tier and rate carried explicitly in the model. Surety capacity confirmed through the ICON/Travelers program.Amber
Klump & ScottJan 2027Equity. Both are ED1 projects nearing RTI and require ~$1.5M of combined preferred equity to fully capitalize; that raise is live.Now inside the Base Case at a January 2027 start (moved from October 2026 on August 23). Not bonded, so no surety dependency.Amber

The honest read: every near-term start is gated on a third-party LIHTC or lender closing, not on LV readiness. Lexington, Riverton and Acama are committed HVN work with GMPs set and buyout underway — the wait is the tax-credit closing calendar, not the contracts. Buyout, staffing and pre-construction are ahead of the closings on all four. The exposure that is genuinely ours to manage is Riverton’s $7.41M of unbought scope, which is priced against a GMP that was set before the current market.

Q2 · Cash available and the 13-week look-forwardAug 3 – Nov 1, 2026 · Base Case
Cash at 7/31 · Actual
$405,563
LV $283,340 · SP $122,223 · was projected at $912,018
Opening 13-Week Cash · 7/31
$405,563
Actual · July close booked August 28
13-Week Low Point
$405,563
The opening balance · before the July 31 receivables collect in August
Closing 11/1 · Net Change
$1,725,965
Net +$1,320,402 · $1,028,928 of it is the July 31 AR / AP unwind
Cash roll-forwardAug 2026Sep 2026Oct 202613-Week Total
Opening cash$405,563$1,400,677$1,450,755$405,563
LV net cash flow (GC net income)$224,210$448,357$332,215$1,004,782
July 31 receivables collected, payables paid$1,028,928$0$0$1,028,928
Gross profit collection lag($84,320)($224,146)$116,142($192,325)
Retention withheld($38,224)($41,569)($40,584)($120,377)
Retention collected$0$0$0$0
Six Peak net cash flow($135,480)($132,563)($132,563)($400,606)
Closing cash$1,400,677$1,450,755$1,725,965+$1,320,402 net
  of which LV (GC)$1,413,934$1,596,575$2,004,348—
  of which Six Peak($13,257)($145,820)($278,383)—

Thirteen weeks from Monday August 3 runs to November 1, so the window is the August, September and October model months. Figures are the Base Case cash roll-forward (LV ending cash + Six Peak ending cash), re-opened on August 28 at the actual July 31 bank balances of $405,563 — $506,455 below the $912,018 the June pack projected for that date. The August column carries the whole July 31 working-capital unwind in one month: $9,463,439 of receivables collected, ($8,434,511) of payables paid, $1,028,928 net. The LV-to-Six-Peak liquidating distribution the June build counted as cash is a non-cash item and was taken out of the cash build on August 29. That is an assumption about timing, not a forecast of August collections, and it is what lifts the balance from $405,563 to $1,400,677. Six Peak on its own goes negative in August and stays there, because the July close removed the Six Peak-to-LV overhead allocation from the projection; on the entity roll-forward LV funds it. The “Total Ending Cash” defect noted in the June pack was corrected in the August 23 model rebuild; the summary line now ties to the entity roll-forward.

Q2a · What has to “bump” to require a cash injectionExcluding capital investment into deals
TriggerSizeWhat it does to cashWatch
Six Peak development-fee timingSP cash ($13.3K) (Aug) → ($278.4K) (Oct) → ($565.0K) (Dec)Not overspend — timing, and now visible from August rather than December because Six Peak carries its full payroll. Six Peak carries the development work on the LIHTC projects (Francis, Deharo, Reseda, 3rd St) years before any of them pays a developer fee. That cost is expensed as incurred while the fee income sits in 2029 and beyond, so the entity runs negative through the back half of 2026 on the Base Case unless LV funds it. LV (GC) cash is comfortable throughout once the July 31 receivables collect.Aug 2026
Another month of Francis delay($155K) cash · ($163K) NI per monthStraight reduction in FY26 ending cash and ~$1.1M of billing pushed out of the year — and it extends the period Six Peak funds Francis development work with no fee against it.Live
The July 31 receivables do not all collect in August$9.46M AR · $8.43M APThe roll-forward assumes every July 31 receivable is collected and every payable paid inside August, for a net $1.03M inflow. If owner draws lag the sub payments by even a few weeks, August runs materially below the $1.40M shown. This is the single largest assumption in the 13 weeks and should be replaced by an actual AR aging.Monthly
Crenshaw retention release slips$77,191 · assumed collected Nov 2026The only retention release inside 2026. If closeout runs past November, the November and December balances are that much thinner at exactly the point the Six Peak balance is at its thinnest.Nov 2026
The SP-to-LV payroll allocation — now removed~$104K/month · ($1.25M/yr)The June pack assumed ~$104K/month of Six Peak payroll allocated into LV job cost. It was never booked in either ledger, and at the July close it was set to zero in the projection; the mechanism stays in the model. The Six Peak burn is therefore ~$133K/month on the roll-forward, the entity goes negative in August, and LV carries it. No allocation is assumed until one is actually booked.Settled in model
Riverton buyout comes in over budget$7.41M open to buyEvery point of adverse buyout on the unbought scope is a direct hit to job gross profit and therefore to LV cash as the job bills.Through 2026
Tax distributionsModeled at $0 for 2026The roll-forward assumes no 30% tax distribution is made in 2026. Any distribution comes straight off the balances above.Policy call
How to read the Six Peak line: LV as a general contractor is not a cash question — it ends the 13 weeks at $2.00M on the roll-forward and builds from there, provided the July 31 receivables collect. The Six Peak balance is thin for a structural reason worth stating plainly: the four LIHTC developments — Francis, Deharo, Reseda and 3rd St — absorb a very large amount of development work and pay no developer fee for years. Entitlement, financing, syndication, closing and construction oversight are all carried at Six Peak and expensed as incurred, while the offsetting fee income in the model — $2.67M on Francis, $3.39M on Reseda, $1.83M on 3rd St — does not begin until 2029. Six Peak is funding a real and growing asset out of current cash: this is a working-capital timing question on work already contracted, not a loss. The bridges are the same either way — the Uplifters fee program, the Klump/Scott capitalization, a broader third-party GC fee base, or a modest working-capital line at Six Peak — none of which requires capital into a deal.
Q2b · WIP and retentionContract-to-complete and cash held back
JobRetention Held TodayAt CompletionRelease
Crenshaw$52,966$77,191Nov 2026
Califa$28,619$99,978Jun 2027
Whipple$28,203$116,250Jun 2027
Ramsgate$56,550$137,453Jul 2027
Nelrose$10,538$30,102Oct 2027
Jobs on site$176,876$460,974—
Mobilizing jobs—$550,1202028–29
In-place book$176,876$1,011,094—
Retention Held · model basis
$176,876
Retention tab not yet rolled to July · draw sheets show $1.61M gross held
Retention at Full Book Completion
$1.01M
Only $77K releases inside 2026
WIP · Contract vs Billed
$93.30M
Backlog on $131.37M contract · $38.07M billed (29%)

Retention from the Base Case Retention tab (5% of LV fee revenue, release at each job’s completion month); the tab was not rolled forward at the July close, so the held-today column is still the June figure. The July draw sheets show gross retention held by owners of $1.61M across the seven billing jobs (Crenshaw $469K, Ramsgate $591K, Califa $230K, Whipple $228K, Nelrose $81K, Francis and Riverton under $10K) — the gross figure includes retention LV in turn holds on its subcontractors. WIP by job — contract value, billed to date, backlog and percent complete — is on the Active Projects tab; margin by job on a YTD and job-to-date basis is on Financial Results; committed-versus-budget cost certainty is on Project Buyout. The over/under-billing view by job — percent billed against percent complete — is now on the Active Projects tab from the July KPI workbook; Ramsgate is 4.7 points under-billed and Crenshaw 1.5 points, everything else is within a point. A full earned-revenue WIP schedule with dollar over/under-billings is the remaining piece; the KPI workbook already holds every input it needs.

Q3 · Budget versus actualsNovember 2025 approved budget · Jan–Jul 2026

As promised in the June pack, the comparison is now against the real anchor: the November 2025 approved budget for 2026, carried on the Budget tab of every model with a Budget vs Actual tab that computes the variance line by line for every closed month. Variance is actual less budget; favorable is positive. The former “Original Budget” (a frozen reforecast seeded with Q1 actuals) is retained as Reforecast Q1 2026 and no longer drives this exhibit.

LineYTD BudgetYTD ActualVarianceJul BudgetJul ActualVariance
GC Revenue$29,368,064$28,534,807($833,257)$5,523,587$7,025,596+$1,502,008
Gross Profit$3,005,239$4,082,836+$1,077,597$554,252$1,766,650+$1,212,398
GC Costs($2,252,307)($2,029,160)+$223,147($322,315)($321,512)+$803
GC Net Income$752,933$2,053,677+$1,300,744$231,937$1,445,138+$1,213,201
Six Peak Revenue$380,693$581,802+$201,109$59,474$78,115+$18,641
Six Peak Expenses($968,369)($1,489,434)($521,065)($137,894)($195,563)($57,669)
Six Peak Net Income($587,675)($854,925)($267,250)($78,420)($118,383)($39,964)
Consolidated Net Income · entity ledgers$165,258$1,198,752+$1,033,494$153,517$1,326,755+$1,173,237

Three things to read from this. First, the GC is ahead of budget on margin, not volume. Revenue is ($833,257) behind the November plan year-to-date, but gross profit is $1,077,597 ahead and overhead $223,147 under, so GC net income is $1,300,744 ahead of a $752,933 budget. July alone is $1,213,201 ahead, and most of that is the Francis bond line billed before its August costs. Second, Six Peak is $267,250 behind budget, almost entirely on expenses (($521,065)): the budget assumed $410,781 of Six Peak payroll would be allocated to LV over seven months and it never was, and consultants and professional fees run well over plan; Six Peak revenue is $201,109 ahead on the June non-cash item and the 12th & Fir fee. Third, consolidated is $1,033,494 ahead of budget on the entity ledgers — but the models, which carry July job margin on the curve, show consolidated $242,368 behind. The gap is the July true-up question on the 7/31 Financials tab. The budget itself carries a known $7,042 internal inconsistency on the allocation line, documented and deliberately not restated.

Q4 · Justin Krueger — wage compliance and certified payrollRaised Jul 14 · resolved Jul 17

What he raised

On July 14 Justin asked whether LV runs weekly certified payroll on all projects, describing it as no longer optional given union pressure on general contractors in California. The underlying exposure is California Labor Code 218.8 / 218.9: on private work, the general contractor is liable for a subcontractor’s unpaid wages and fringe benefits. Unions have been approaching non-union subcontractors’ workers, finding compensation defects and suing the sub and the GC. None of LV’s jobs are prevailing-wage, so certified payroll in the formal sense does not apply — but the wage liability does.

How we addressed it

We engaged Greg Korbel of Miller, Morton, Caillat & Nevis and met on July 17. His read: the GC cannot escape liability for a sub’s unpaid wages, but penalties and liquidated damages — which exceed the wages themselves — are avoidable if the contractor monitors sub payroll, acts on any failure, and obtains a sworn affidavit before final payment. LV’s subcontracts already carry the right to demand this documentation and to withhold payment until it is produced.

The three procedures now being implemented: (1) every subcontractor submits pay stubs for all employees on the job each pay period; (2) those stubs must carry everything Labor Code 226(a) requires — gross wages, hours, rates, deductions, net wages, pay period, employee and employer identification; (3) every subcontractor signs an affidavit of payment of wages and fringe benefits before final payment. Grady is implementing this across the book, with case-by-case deviation possible depending on the subcontractor and the client’s needs. Justin confirmed alignment on July 17 and added that records should be retained for years after project close, and that any rumbling of non-payment must be acted on immediately rather than ignored. Status: agreed and in rollout — no open disagreement with Justin on this issue.

Legal cost for the review was billed to 2859 Francis. This item is carried as a portfolio-level entry on the risk register below, rated amber until the paystub-and-affidavit procedure is confirmed live across every active subcontract rather than newly executed ones.

Q5 · Deals where Six Peak holds a stake, fee or promoteStanding tracker · Base Case
DealSix Peak PositionFY26 to Six PeakLife of DealNotes
RamsgateGC + Developer · development fee$286,875$602,437$430,312 construction-period fee plus three occupancy tranches of $57,375 at 20% / 50% / 90% lease-up
CrenshawGC + Developer · development fee$93,750$93,750Fully recognized in FY26 as the job completes
12th & FirDeveloper fee$91,500$285,000First $44,000 booked in July; runs beyond FY26; not an LV construction job
APA LLP50% share of entity net income$59,783$158,270Equity position, not a fee — carried on its own projection tab
EdgemontManagement fee$6,667$6,667$833/month, runs off in 2026
FrancisGC + Developer · LIHTC share$0$2,670,460Steyn guaranty attached; distributions begin Sep 2029 (month 42)
ResedaGC + Developer · LIHTC share$0$3,389,891$45.3M project, not yet funded · May 2027 modeled start
3rd StGC + Developer · LIHTC share$0$1,828,876$41.4M project · 2028 start in the model
Klump & ScottGC + Developer · accounting, developer and guarantee fees$0In Base Case from Jan 2027Both jobs are now inside the Base Case at a January 2027 start; fee streams switch on when the ~$1.5M preferred equity closes
UpliftersDevelopment-fee program · 10% SP overhead + tiered bonusNot in Base$4.10M in Uplifters plans60-property program led by Schuyler Dietz · no capital required
DeharoPlaceholder — under constructionTo confirmTo confirmNot currently carried in the model or in this pack. A LIHTC development under construction — like Francis, Reseda and 3rd St it absorbs Six Peak development work today against a fee that is years out. Position, fee basis and YTD figures to be confirmed and added — flagged for discussion on the call.

Sourced from the Base Case model — the Projects tab flags each job as “GC + Developer” or “3rd Party GC”, and the Six Peak revenue block carries each fee line by month. Califa, Whipple, Nelrose, Lexington, Riverton and Acama are third-party GC contracts with no Six Peak development position. Important framing on the LIHTC lines: these four developments — Francis, Deharo, Reseda and 3rd St — require more development work than anything else in the portfolio and pay no developer fee today; the modeled distributions do not begin until 2029. On top of that, under the current rate and tax-credit environment the Steyn cost of capital absorbs most of the early LIHTC distributions, so through FY2033 the net contribution of the strategy is close to zero — the meaningful development-fee income lands after 2033. This is the single biggest reason the Six Peak entity P&L reads negative while the underlying book grows. The life-of-deal figures above are gross Six Peak share, before that Steyn absorption. This table becomes a standing exhibit and will carry actual-versus-projected columns once Deharo and any other omitted positions are confirmed.

Q6 · Project-level dashboardsWhat happened and what comes back

What was lost

The earlier draft pack carried two job-level exhibits that this portal does not: a WIP report with job-level KPIs (contract value, change orders, CO ratio, % billed, % complete, YTD and JTD gross and net margin, % buyout, buyout savings and savings ratio by job) and a metrics dashboard of backlog/burn, book-to-bill, bid pipeline and hit rate, DSO, PM retention, client concentration and bonding capacity. They were dropped when the portal was rebuilt on live data — those exhibits were built with placeholder values, and the rebuild took the position that nothing goes in the pack unless it is sourced.

What comes back, and live

The job-level WIP and KPI table returns in full: every column in that exhibit except change-order win rate is already computable from the KPI workbook and the monthly Buyout Reports. On the metrics dashboard, backlog/burn, book-to-bill, bid pipeline, hit rate, client concentration and bonding capacity are all derivable today. DSO, PM retention and change-order win rate are not — they need a receivables aging feed and a change-order log that does not exist yet. Those three will be shown as “not yet instrumented” rather than filled with an estimate.

Q7 · Job and site risk registerFirst pass · traffic lights from current data

Operational Metrics today carries one aggregate safety box. Below is the first pass at the job-level register, rated only where there is data behind the rating. It will be maintained monthly and expanded — schedule variance in particular needs a baseline-versus-current schedule feed that is not yet in the reporting pack.

JobSafetyCost / BuyoutScheduleFinancingMarginDriver of the worst rating
CrenshawGGAGG80% complete, substantial completion December 1 per the July 28 schedule — closeout and the $77K retention release are the open items
RamsgateGAGGG91.3% bought out, but the buyout report is April-vintage — data currency, not cost concern
CalifaGGGGG90.8% bought out, 5% YTD net margin, on schedule — no flags
WhippleGGGGG91.7% bought out, 8% job-to-date net margin — the strongest job in the book
NelroseGAGGA(1%) YTD and (6%) job-to-date net margin on a $4.2M job; no current buyout report
Francisn/aAAGAClosed August 13, construction started in August; first pay application of $852K booked in July, $839K of it the bond line with the $314K premium and the Krueger payment landing in August — watch the August job P&L for the reversal
Rivertonn/aRAAn/a48.3% bought out with $7.41M still open to market pricing — the book’s largest cost exposure
Lexingtonn/aAAAn/aPre-construction buyout in progress; start moved to September 2026, contingent on close
Acaman/aAAAn/aTier 2 bonding at a 3.25% rate versus 0.72–0.74% elsewhere in the book — bond cost is a live GMP input
Portfolio · wage complianceA————Labor Code 218.8/218.9 procedure agreed and in rollout; amber until confirmed live across every active subcontract

Ratings: G = no action required; A = watch item with a named owner; R = escalated, on the board agenda. Safety ratings reflect the monthly third-party inspections by Safety Compliance Company at each active site — the latest filed (Ramsgate, June 16) covered 52 items with 39 satisfactory and zero unsatisfactory findings, so every active site rates green on safety — July inspection reports were not in Box when this pack was built; jobs not yet on site are not rated. Cost/buyout is rated from each job’s Buyout Report; margin from the Financial Results tab; financing from the closing status above. Schedule is rated conservatively from percent-complete against modeled job end, because a proper baseline-versus-current schedule feed is not yet part of the monthly reporting — instrumenting that is the main gap in this register.

Q8 · Warranty and reworkWhat is captured today
Warranty & job adjustmentsBooked% of Revenue
January$17,6611.2%
February$5,7990.2%
March$3,4320.1%
April$0—
May$73,8741.7%
June$0—
July$0—
Jan–Jul 2026$100,7660.35%
Forward assumption$5,000/mo~0.08%

It is online today, but only as a single blended general-ledger account — 5900-1040, Warranty and Other Job Adjustments. January through July booked $100,766, or 0.35% of the $28.53M of revenue, against a model assumption of $5,000/month; nothing was booked in June or July. The May charge of $73,874 is the item that moved the month and is called out in the June 30 financials.

What that account cannot tell you: which job the cost belongs to, whether it was warranty callback, rework of defective work, or an unrelated job adjustment, and whether it was recoverable from a subcontractor. A rate of 0.35% is well inside a normal range for a GC — but the number is not yet reliable enough to manage against, because a single account that mixes three cost types will not show a trend until it is split.

The change: split 5900-1040 into job-coded warranty, rework and other-adjustment codes, add a callback log at closeout, and report warranty and rework as a percentage of completed revenue by job with a target under 1%. Crenshaw closing out in the fourth quarter is the first job that will produce a clean full-cycle warranty figure.

What changes in the next pack: five items become standing exhibits — the signed / funded / on-site ladder, the 13-week cash roll-forward, budget-versus-actual against a re-anchored budget, the stake-and-promote tracker, and the job-level risk register. Three additions require instrumentation that does not exist yet and will be shown as gaps until it does: a true WIP over/under-billing schedule, a baseline-versus-current schedule feed for the risk register, and split warranty/rework cost codes. Deharo is carried as an open item for the call. The July pack delivers two of the three: budget-versus-actual is now against the November 2025 budget and the over/under-billing view is on Active Projects; the schedule feed and the warranty code split remain open. Where a number cannot be sourced, this pack will say so rather than estimate it.
01 / 09Overview
Use ← → arrows to advance