← Back to portal
Six Peak Capital · LV Construction · Operations

LV Construction Operations Portal

Project status, bonding capacity, and operational tracking for the LV Construction GC platform. Use the section tabs or ← → arrows to move through the deck.

Now showingOverview
01 / 04
Current as of April 2026
01 · Overview · Current as of April 2026

LV Construction — operations at a glance

A snapshot of the active construction book, bonding utilization, and operational health across the LV portfolio. Nine projects are in flight against a $150M bonding line, with a clean safety record and a healthy available-to-bid balance.

PLACEHOLDER DATA: All figures below are illustrative. The production LV Construction tracking portal will wire live data from project management, accounting, and bonding systems.
Portfolio SnapshotActive book · bonding · operations
Active Projects
9
$148.3M aggregate GMP
Bonding Available
$60.1M
Ready to bid
Revenue-to-Date (FY26)
$6.4M
On plan (+2.1%)
OSHA Recordables (YTD)
0
TRIR 0.00 · trailing 12mo
Read of the book: The active portfolio runs $148.3M of GMP across nine projects, from Crenshaw in wrap-up to Acama in pre-construction. Bonding is 60% utilized against the $150M line, leaving $60.1M available to bid. Operationally the platform is clean — zero OSHA recordables, zero subcontractor defaults, and a portfolio averaging two days ahead of schedule.
02 · Active Projects & Status

The active construction book

Nine projects in flight totaling $148.3M of GMP. Crenshaw is in wrap-up; the bulk of the book is on schedule, with Lexington and Denny starting and Acama in pre-construction.

ProjectGMP% CompleteScheduled EndStatus
Crenshaw$5.3M82%Nov 2026Wrap-Up
Ramsgate$20.0M34%Jul 2027On Schedule
Califa$11.7M41%Jun 2027On Schedule
Whipple$13.5M38%Jun 2027On Schedule
Nelrose$4.1M29%Oct 2027On Schedule
Francis$43.0M12%Dec 2028On Schedule
Lexington$13.6M3%Apr 2028Starting
Denny$15.8M3%Mar 2029Starting
Acama$21.3M0%Oct 2028Pre-construction

Percent-complete and status are illustrative placeholders. GMP values shown are remaining contract balances for projects under construction.

03 · Bonding Capacity

Bonding line · $150M aggregate

The surety line supports $150M aggregate with a $75M single-project cap. The book currently draws 60% of capacity, leaving $60.1M available against incoming bids.

Total Capacity
$150.0M
Single project: $75M
Outstanding
$89.9M
60% utilized
Available
$60.1M
Ready to bid

Utilization · 60% of $150M

60%

Liquidity held against the 2.5% reserve requirement: $2.25M · Surplus over reserve: $1.12M.

Headroom: With $60.1M available and a $75M single-project cap, LV can underwrite additional mid-size awards without renegotiating the line. Reserve coverage carries a $1.12M surplus.
04 · Operational Metrics

Operational health

Safety, change orders, revenue pacing, and schedule variance across the active portfolio. The platform is clean on safety and subcontractor risk, with revenue running slightly ahead of plan.

Safety — OSHA Recordables (YTD)
0
Trailing 12-month TRIR: 0.00
Open Change Orders
23
$1.84M · avg age 18 days
Revenue-to-Date (FY26)
$6.4M
On plan (+2.1%)
Schedule Variance (Portfolio Avg)
+2 days
2 behind · 7 on/ahead
Subcontractor Defaults
0
Last 12 months
Upcoming Closeouts (90d)
1
Crenshaw — Nov 2026
Methodology: Metrics are illustrative placeholders pending live integration. Safety figures follow OSHA recordable definitions; schedule variance is the GMP-weighted portfolio average against baseline.
01 / 04Overview
Use arrows to advance